Streetscape Update

On Thursday, Hutch-N-Son Construction was able to prep for new sidewalk construction between Spring and Ann streets as part of the City of Walhalla’s Streetscape Project. On Friday, they plan to pour 20 cubic yards of concrete for the new sidewalks. In addition, electrical work continues today between Catherine and Spring streets. Hutch-N-Son Construction plans to pour concrete Saturday and continue the sidewalk construction. They expect to finish the block in front of the businesses by Monday night.